Patients who have undergone thyroid surgery and have thyroid cancer are treated with RAI (I-131) atomic therapy. After RAI treatment, patients are kept in private rooms for a while and hospitalized. The toilets and bathrooms of the patients in these rooms are collected directly in the waste tanks available in the hospital, and the I-131 present in the patient’s feces is given to the city sewer at the end of a certain period of time.
In order for the system to function correctly and to disrupt the treatment times, the waste tank system must be checked and maintained at certain periods. Our company provides this service throughout Turkey with its competent and experienced staff. Apart from maintenance, we ensure that the system remains active continuously by intervening in the malfunctions in these systems in a very short time.




Periodic Maintenance of Our Company
System Control
Testing and reporting of the entire system, including drainage pumps, from operating it in manual mode to giving it to the sewer at the waste entrance.
Tank Cleaning
- Mud-style dirt on the tank floor and body is cleaned.
- The inside of the tank is washed with the mixture obtained by preparing a 10 percent special cleaning solution and water.
- After the mixture is set to remain for 20 minutes, the solution is cleaned by washing with water.
Leak Control in Tanks
- Check for holes, deficiencies or cracks that may be on the tank.
- Cracks that may occur in tank connections, connection control.
Control of Pumps
- Control of electrical values
- When the pump is put into operation, the current, voltage and pressure values should be checked and it should be checked whether there are changes in these values over time.
- The bearings should be checked by disassembling the motor.
- Oil seals and mechanical seals are reviewed.
- The sealing elements of the engine are checked. It is checked whether there are any negativities such as puncture, crushing, fragmentation, tearing, etc. in the energy cables.
- Hose or pipe connections are checked.
- If there is a blockage in the bulk check valves, they are checked.
- It is checked whether there are hard-threaded fibers, wires and similar objects stuck in the pump.
- In float pumps, it is checked whether the floater (ON-OFF) is made.
Panel Maintenance
- The control panel setting and working setup are controlled.
- Voltage and current values measurement and control
- Switchgear material heating controls
- Defective switchgear material replacements (fuse, contactor, relay, etc.)
- Panel interior cleaning
- Connection terminals controls